Flooring Renovation Update – 7/26

Here are the latest updates for you regarding our flooring renovations:

Level 3unfortunately there are still some study carrels that have not been carpeted and we are awaiting an estimate of when they will be available. 

Level 1 & Level 2 Bathrooms – are currently off line and are being worked on.  The demo should be mostly done and they will be working on the new tiles soon.

Plaza Level – They made record time in this area and are done with the carpeting behind the iDesk.  Staff will be moving back into their offices through the early part of next week.

Level 1 – For those who have been on Level 1, you will see that although it is in a constant state of motion, they are moving along rapidly and that is great news.  The majority of the North side is done and they will continue in a counter-clockwise pattern around the floor.

The Q Center is still able to follow their summer hours, they are just on the South side of the floor.  If you are looking for the Digital Learning Center, Steve Park is temporarily located in the staff area of Level 1.  If you need his assistance, please stop by the help desk on that floor.