The flooring project is moving along here in the final weeks of the summer. Here’s where we are at:
Level 3 – is open for business, including all of the study carrels. There are some odds and ends still to do, including moving back of furniture, but it should not affect the use of the 3rd floor. Tomorrow they will begin on the Graduate Student Study Center.
Level 1 & Level 2 Bathrooms – should be completed by the middle of next week.
Plaza Level – The staff area behind the iDesk is completed and this week they have been working on the Auriemma Reading Room, the staff lounge and the 24-hour study room. They should be cleared of those areas later this week. The Auriemma Reading Room will stay off line for a bit longer, as it will be the space where the administrative office furniture will be stored when that space is done. That space, and the Class of ’47 are the last pieces to be done on the Plaza Level.
Level 1 – is completed in terms of the bulk of the carpeting. As on Level 3, there is clean-up and pieces that still need to be done. We also will be working on getting the furniture back where it belongs next week. The Q Center is open, and the W Center should be back in operation next week. The Digital Learning Center and our own help desk are also working to get their space back in working order.