Flooring Update — June 24

The past two weeks have been a bit frustrating on the flooring project as we found some items outside the scope of the project that needed to be fixed before the project could continue. But things are looking up now. The bathrooms should see a team of plumbers on site Monday (today) fixing the old floor drains. They should be finished with level 3 and 4 by Weds. Which means the tile installers will be able to finish the water proofing and the tiling.

The carpet guys had hit something that turned out to be a major hurtle for them. The carpet is very difficult to pull up, making the preparation for the carpet installation much longer than anyone anticipated. The good news is they started laying carpet on Friday and they worked all day yesterday (Saturday); so they have made great progress in the past two days. The third floor still remains closed to patrons but open to library staff to retrieve items for our patrons.

As of today, the level 4 lobby will be closed for about 2 weeks. To access level 4 please use the corner emergency stairwells (except the SW stairwell as that is alarmed). To access MAGIC (the Map Library), contact the staff of MAGIC, and they will meet you on the plaza level and then take you up via the staff elevator. Please contact them at: 860-486-4589. http://magic.lib.uconn.edu/

We are watching the schedule very closely and I will update you more often now that we are seeing the progress in the different parts of this installation.

Thank you for your patience.

Leave a Reply

Your email address will not be published.